HomeGuides › Draw schedules

Build a draw schedule that keeps you cash-positive

A profitable job and a job that pays you on time are two different things. Plenty of contractors make 25% on paper and still borrow against a credit card in week three — because the schedule they wrote collects the money after they've already spent it.

Last reviewed: August 2026 · 8 min read

The short version. Tie every draw to a physical milestone you can point at, sequence them so each draw lands before you pay for the phase it funds, and keep the final payment small — 5–10%.

Same $60,000 kitchen, same 25% margin, two schedules: the eight-draw version below never dips below zero. The three-draw version has you $21,800 out of pocket at its worst point.

Three rules, then the example

1

Milestones, not dates

"Rough-in inspection passed" beats "week 3" every time. A physical milestone is verifiable by walking the job — nobody argues about whether drywall is hung. A date-based draw invites a fight every time a supplier is late, and in states that require progress payments not to exceed the value of work actually performed, a calendar-triggered payment can be non-compliant as well as awkward.

Write milestones a stranger could check: "demolition complete and debris removed", not "demo phase substantially underway."

2

Money in before money out

For each phase, ask: what do I have to pay, and when does the draw covering it arrive? If the cabinet supplier wants 50% at order and your cabinet draw is at installation, you've just volunteered to lend the client $7,000 for six weeks. Move the draw to the order, or get supplier terms — but don't leave the gap in and hope.

3

Keep the tail short

The final payment should be small enough that it isn't worth holding hostage over a scuffed baseboard, and big enough that you'll still show up for the punch list. Somewhere in the 5–10% range. A 30% final payment turns your last two days into a negotiation you can't win, because they have the money and you have already done the work.

Worked example: a $60,000 kitchen

California job, so the deposit is capped at $1,000 — the "$1,000 or 10%, whichever is less" rule, which on any contract over $10,000 means a flat $1,000. (If that's news, read deposit limits by state first — it changes how the front of every schedule has to be built.) Assume $45,000 of direct cost and $15,000 of gross profit.

#Milestone that triggers it% of contractDrawCumulative
1Contract signed — statutory deposit cap1.7%$1,000$1,000
2Cabinets & windows ordered — special-order deposit15.0%$9,000$10,000
3Demolition complete, debris removed12.0%$7,200$17,200
4Rough plumbing, electrical & HVAC in, inspection passed18.0%$10,800$28,000
5Drywall hung, taped and primed15.0%$9,000$37,000
6Cabinets set, countertop templated20.0%$12,000$49,000
7Tile, paint, trim and fixtures complete12.0%$7,200$56,200
8Substantial completion, written punch list issued6.3%$3,800$60,000
Contract total100%$60,000

Draw 2 deserves a note. Cabinets and windows are usually the biggest and earliest cash outlay on a kitchen, and they're ordered long before they're installed. Several states explicitly allow the actual cost of special-order materials in addition to the deposit; others don't, and in "value of work performed" states you should check with your attorney how delivered-but-uninstalled material is treated. Whatever your state allows, put the draw at the order, not at the installation — that single placement decision is worth more to your cash position than the other seven combined.

Now the part nobody puts in a template: the cash position

A draw schedule is only good if you check it against the outflow. Here's the same job with what you actually pay out at each stage:

StageCash inCash outYour position
Contract signed+$1,000+$1,000
Cabinets & windows ordered (50% supplier deposit)+$9,000−$7,000+$3,000
Demo (labor + dumpster)+$7,200−$3,300+$6,900
Rough-in (MEP subs)+$10,800−$8,000+$9,700
Drywall+$9,000−$4,500+$14,200
Cabinets set (balance + countertop + install)+$12,000−$13,000+$13,200
Finishes (tile, paint, trim, fixtures)+$7,200−$8,000+$12,400
Substantial completion (punch)+$3,800−$1,200+$15,000
Totals$60,000$45,000$15,000 profit

Never negative. Not once. The two stages where outflow exceeds the draw — cabinets and finishes — are absorbed by the cushion built up earlier, which is exactly what the cushion is for.

The same job on a three-draw schedule

Now the version most contractors actually write, because it's the one clients propose: deposit, halfway, completion.

StageCash inCumulative outYour position
Contract signed+$1,000$0+$1,000
Cabinets & windows ordered$7,000−$6,000
Demo complete$10,300−$9,300
Rough-in complete$18,300−$17,300
Drywall done — the day before the "halfway" draw$22,800−$21,800
"Halfway" draw arrives+$29,000$22,800+$7,200
Cabinets, finishes, punch$45,000−$15,000
Final payment+$30,000$45,000$15,000 profit

Identical job. Identical profit. Identical client. The only difference is where the draws sit — and it's the difference between never touching your own money and being $21,800 underwater on a $60,000 kitchen, twice, while carrying a $30,000 final payment you now desperately need.

And notice the compounding risk. In the three-draw version, the moment the job goes sideways — a client dispute, a discovered structural problem, a change order argument — you're already tens of thousands down. In the eight-draw version, the worst case at any point is that you stop work roughly even. Draw scheduling isn't just cash flow; it's how much of the job's risk you're personally financing.

Two phrases that strand your final payment

✗ Don't write"Final payment due upon the Owner's complete satisfaction with the Work."
✓ Write instead"Final payment due upon Substantial Completion. Contractor shall issue a written punch list at Substantial Completion; Owner may withhold 150% of the reasonable value of remaining punch list items, released upon their completion."

"Complete satisfaction" is a subjective standard with no defined endpoint. A client who is unhappy about something unrelated — a delay, a neighbour, a countertop they chose themselves — has an unlimited hook to hang it on. Substantial completion is an objective, defined moment; the punch list is a finite, written list; the holdback gives them real protection while capping your exposure at the value of the actual remaining work.

✗ Don't write"Final payment due upon final inspection and issuance of the certificate of occupancy."
✓ Write instead"Final payment due upon Substantial Completion. A holdback of $____ shall be retained solely against items requiring final inspection sign-off, released within 5 days of sign-off."

The second version doesn't hand your entire final payment to a building department's scheduling calendar. If the inspector is booked three weeks out, or the delay is on something the owner supplied, you're not the one financing the wait. Carve out only the piece that genuinely depends on the inspection.

One more clause worth having, and one to strike. Have a suspension-for-nonpayment clause: if a draw goes unpaid past a stated number of days, you may suspend work without breaching, and the schedule extends accordingly. Without it, stopping work over nonpayment can put you in default. And strike any language making your payment contingent on the owner's financing or loan draw arriving — that's their arrangement, not your risk to carry.

Protect the back end too

A schedule is your first line of defence; mechanic's lien rights are the backstop. In most states those rights depend on a preliminary or pre-lien notice served early in the job — California, for example, generally requires a preliminary notice within 20 days of first furnishing labor or materials — and missing that window can forfeit the lien entirely, no matter how right you are about the money.

Deadlines, forms, and who must be served vary enormously by state and by whether you're a prime or a sub. Find out your state's rule once, build serving the notice into your job-start checklist, and it costs you a stamp instead of a receivable. Don't take the 20 days as gospel outside California — confirm your own state's deadline with a construction attorney.

How this works in BuildCraft Pro

Write the schedule on the Contract tab under Payment Terms — either freehand or with the AI draft as a starting point — then bill against it from Invoicing:

What the app won't do is tell you whether the schedule is sequenced right — that's the cash-out column, and only you know your supplier terms. Build the schedule against your actual outflow once, and you can reuse the pattern on every kitchen after it.

Frequently asked questions

How many draws should a remodel have?

Enough that you're never funding the job. For a $40,000–$80,000 kitchen or bath, that's usually six to eight tied to physical milestones. More draws don't change what you collect in total — only how long you're out of pocket between spending and getting paid.

Should draws be tied to dates or milestones?

Milestones, and physical ones. "Rough-in inspection passed" can be verified by looking; "week 3" starts an argument the first time a supplier is late. In states requiring progress payments not to exceed the value of work performed, date-triggered draws can also be non-compliant.

How big should the final payment be?

5–10% of the contract is a common range. Small enough that it isn't worth withholding over a paint touch-up, large enough that you'll come back and finish the list.

What if the client wants fewer, bigger draws?

Explain it as scheduling rather than trust: more frequent draws mean you're paying subs and suppliers on time, which is what keeps their job moving. If they still insist, price the float — carrying $20,000 for a month has a real cost — or decline the job. What you shouldn't do is accept the schedule and absorb the cost silently, which is the option most contractors take.

Can I bill for materials before they're installed?

It depends on your state and how its rules treat delivered-but-uninstalled materials, and it's the single most common place a well-intentioned schedule goes non-compliant. In states with a value-of-work-performed test, get specific advice before you write a materials draw. Where it's allowed, tie it to delivery to the site with a receipt attached, not to the order date.

Do change orders get their own draw?

Say so explicitly on each change order — either billed with a specific progress payment or invoiced separately on completion. That's not just tidiness; in California, stating the effect on the schedule of progress payments is one of the things a change order is legally required to contain. See how to write a change order that actually gets signed.

Bill your draws in one click

Set the schedule on the Contract tab, then hit Deposit, Draw, or Remaining from Invoicing — with live Invoiced, Collected, and Outstanding totals. 14-day free trial — $0 today.

🎁 Start 14-day free trial →
Keep reading Deposit limits by state: how much can you legally collect up front? → How to write a change order that actually gets signed → Markup vs. margin: why a 20% markup is not 20% profit → How to Estimate a Kitchen Remodel → All guides →
General business information for contractors — not legal, tax, or accounting advice, and no attorney–client relationship is created by reading it. Every dollar figure is illustrative arithmetic, not a recommended schedule for your business. Payment schedule rules, progress payment restrictions, and mechanic's lien notice deadlines vary by state and change; the contract language shown is a starting point for discussion with a construction attorney licensed in your state, not a drafted clause you should use as-is.